Wednesday, January 23, 2013

Basement Two

I am so excited. The basement is moving along at a rapid pace and we are on track for the 8 to 10 week timeline.

Framing is finished and we did a walk-thru of where we want light switches, electrical outlets, cable and phone jacks, as well as the placement of overhead lighting.

The electrician come tomorrow and the plumber on Saturday.

Then we wait for inspection which is currently 1 to 2 weeks out. Once inspection is passed they will insulate and put up the drywall.

Here are the latest pictures of the progress.


*View from the top of the stairs*


*Main wall at the bottom of the stairs. There are two built in art niches to break up the flat wall*

*Bedroom/Craft room*





*Bdrm/craft room

View from outside the bdrm/craft room*

*They have removed the piece of wall to open it up. It will be finished with a rail and ballisters matching what we have upstairs*



*This will be the wall the TV is mounted on*

*The couch will be along this wall*

*Another view of the open stairs*